Caisson Seawalls

Breakwater Construction

Returning to Hitachinaka, here again is an aerial view of the area, looking toward the east:

Figure 1:  Aerial view of Hitachinaka, Japan, June 2005. [JonHanson]

Note the offshore breakwater seawall in upper left portion of the aerial photograph. That seawall has since been extended southward (toward the right in that view).

Extending the Hitachinaka seawall required floating caissons 3 km to the end of the seawall. Following is an aerial view looking north:

Figure 2:  View of Hitachinaka port, looking north. Caissons had to be floated 3 kilometers to the south end of the breakwater. [MLIT]

The caissons were in seawater curing position near the port (may have been constructed on land but were in sea water to cure the concrete). Large tug boats floated the caissons from the curing position to the end of the breakwater seawall.

Figure 3:  Caisson is pulled out from a row of caissons curing near the port, while water is being pumped out of the caisson to make it float. [MLIT]

Figure 4:  Large tugboat pulls the caisson. The caisson is floating higher. Water continues to be pumped out, to increase flotation. [MLIT]

Figure 5:  The end of the breakwater awaits the new caisson. The portion of the breakwater to the right of the wave wall are new caissons already in position. [MLIT]

Figure 6:  The new caisson approaching the scene. [MLIT]

Figure 7:  The new caisson approaching the end of the breakwater. [MLIT]

Figure 8:  The larger tug boats provide line tension to prevent lateral drift, while other tugs push the new caisson into the breakwater. [MLIT]

Figure 9:  Large tug boat providing line tension to prevent lateral drift of the caisson, before the caisson is connected to the breakwater. [MLIT]

Figure 10:  Large winches and steel cables pull the new caisson into the breakwater. Crane barge with spuds (stilts) in up position shown at right. [MLIT]

Figure 11:  Crane barge has lowered its spuds into the seabed, making it stable and ready to dump fill into the cells of the new caisson. Water is pumping out of the caisson in preparation for filling the cells. [MLIT]

Video

Short video:  Damped oscillation on harbor side, as another large tug is providing longitudinal tension on the ocean side (to the left, not shown). [MLIT]

< Previous page:  Seawater Construct

Caisson Seawalls

Page 1 : 
Page 2 : 
Page 3 : 
Page 4 : 
Page 5 : 
Page 6 : 
Page 7 : 
Page 8 : 
Page 9 : 
Page 10 : 
Page 11 : 
Introduction
Quays
Quay Construction
Singapore
Tema, Ghana
Le Portier, Monaco
Colombo, Sri Lanka
Hitachinaka, Japan
Slip Form
Seawater Construct
Breakwater (this page)

Return to:  AEC | Caisson Seawalls

NewUnivStudies.org